Sewage treatment plant for a factory

ClearFox® SBR system for a plasterboard factory in Bulgaria

Project Details

Size
20 PE
Location
Bulgaria
Completed
2016

Project Delivery

Features
Wastewater treatment for direct discharge into a receiving waterbody
Treatment Modules

Project Results

Before
After
COD
1500 mg/l
100 mg/l
BOD
800 mg/l
25 mg/l

Discussion

Situation

A company for building materials opened a new plant in the south of Bulgaria. There, around 40 employees work in shifts to produce plasterboards, which the company exports throughout Europe. While planning the new plant, those responsible for the project decided on a wastewater treatment plant to treat the wastewater. This is exclusively sanitary wastewater that accumulates during working hours.

Problem

The first challenge in this project was the high standard of purification, as the wastewater was to be suitable for direct discharge into a receiving water body. The effluent values should therefore be below the following values: COD 100 mg/l, BOD5 25 mg/l and filterable substances 75 mg/l. The second challenge was the limited space on the company premises. Therefore, the wastewater treatment plant had to be particularly compact.

Solution

To meet all customer requirements best, the ClearFox® team opted for an SBR system in tanks. These are rotationally moulded and therefore have no predetermined breaking point. This makes them particularly stable, durable, and suitable for both above-ground and below-ground installation.

The ClearFox® team assembled the treatment plant from a total of seven tanks. At the beginning, the wastewater flows through a drum filter to separate the first coarse solids from the wastewater. The first three tanks serve as buffer storage to compensate for the irregular wastewater load. From there, the plant pumps the wastewater into two more tanks in which the SBR system is installed. This is where the biological treatment takes place. The powerful aeration system supplies the wastewater with oxygen and thus ensures the growth of microorganisms.

The sludge produced in the process is stored in the two remaining tanks. As the entire treatment plant works very efficiently, the sludge largely decomposes by itself, which is why the sludge only needs to be removed once a year. For this project, the ClearFox® team took over the complete project planning, the construction of the tank system, the installation and commissioning on site as well as the training of the employees.

FAQ

The ClearFox® SBR system is flexible and can treat sanitary wastewater as well as industrial wastewater with comparable requirements. A precise analysis of the wastewater composition is required in order to optimally design the system.

Yes, the buffer tanks balance out irregular wastewater loads so that the system operates reliably even with fluctuating quantities.

Maintenance is minimal as the sludge largely respires itself. Removal of the sludge is usually only necessary once a year.

The duration depends on the individual project requirements; usually the planning, installation and commissioning can be completed in a few weeks to months.

The plant will be designed to comply with all local and European regulations for the discharge of treated wastewater into a receiving water body.

Project Gallery

Featured Modules

Similar Projects

Have A Question? Get In Touch.
Item #3